How we build and check

Nobody checks their own homework.

Installing a lift is careful, ordered work. Here is how a project moves from order to handover, and the five standard checkpoints along the way. We show you our checks so you can see them for yourself.

The journey

Seven stages from order to handover.

The details differ for each home, but the shape is the same.

01Order confirmedScope, drawings and plan agreed in writing.
02DesignYour drawing is approved before we make anything.
03Site readinessWho does what on site is clear from day one.
04ProductionYour lift is made to your drawing.
05DeliveryPacked, labelled and counted on the way out and at site.
06InstallationBuilt stage by stage, with checkpoints along the way.
07HandoverA walk-through, a demonstration and your documents.
Five checkpoints

The moments where we stop and check.

At each checkpoint the work stops until a second person, not the one who did the work, has inspected it. If a point fails, we fix it and inspect that point again.

H0
Before anything is dispatched

Is the site ready?

The cheapest problem to fix is the one found before a truck leaves. We confirm the site matches the drawing before we send your lift.

  • Shaft, pit and overhead match the drawing
  • The pit is dry and sealed
  • Floor levels are marked on every floor
  • Debris cleared and open edges made safe
  • Three-phase power and earthing ready at the machine point
  • A lockable store and vehicle access
  • Clear working space at each entrance
  • Painting, covering and civil work windows agreed with you
Inspected: the site against the drawing
H1
After the shaft is set up

Is the shaft true?

A lift can only run as straight as the shaft it lives in. We measure the shaft over its full height before a single rail goes up.

  • Shaft is plumb over its full height
  • Landing openings are square and the right size
  • Pit and overhead are as drawn
  • A template proves the car will fit with proper clearances
  • Welds and primer are complete, or the civil shaft is finished
Inspected: shaft plumb, openings square, pit and overhead as drawn
H2
After rails and cylinder are fitted

Are the rails and cylinder right?

This is where ride quality is won or lost. The rails, the cylinder and the pulley all have to line up.

  • Rail spacing measured at every bracket
  • Rail joints flush, with no twist
  • Cylinder upright and the pulley aligned
  • Hose connected without strain and without leaks
  • Panel and power unit fixed and earthed, oil at the right level
Inspected: rails, cylinder and pulley alignment
H3
Once the car can run

Does the car run safely?

Before the lift is used for anything else, we put it through its paces and test the safety circuit.

  • The car moves smoothly over its full travel
  • Rope tensions are equal
  • Running clearance is right at every floor
  • Every landing door lock is proven to break the safety circuit
  • Limit switches cut the lift where they should
  • Earthing is in place and wiring on the car top protected
  • The toe guard under the car is fixed
Inspected: running, door locks and the safety circuit
H4
Before handover, with you

Final check, together

The last checkpoint happens with you in the room. We test, you watch, and anything that needs a touch-up goes on a written snag list.

  • Overload warning and lock-out tested
  • A load test, with readings recorded
  • Emergency lowering brings the car to a floor
  • Alarm and, where fitted, intercom tested
  • Floor levels and door operation checked
  • Earthing and insulation readings recorded
  • Cabin cleaned and capacity plate fixed
  • You walk through the lift and we list any snags
Inspected together with you, in the room

These are our standard checkpoints. We may add to them or adapt them to suit your lift, your building and your site.

Our records

How you can tell it was done.

Photos and readings

When a step is finished, the person who did it records it: a count, a photo, sometimes a measurement. If you ever ask "was that done?", there is a record.

Packed, counted, photographed

Material leaves our workshop in labelled kits, counted and photographed. On arrival at your site the crew counts them again against the labels. Missing parts are found early.

Updates from site

The crew reports in as work progresses, and the office follows up on anything holding things up. We tell you about changes and decisions as they happen.

Follow your project

See where your lift is, from your phone.

We give you a private login. It shows the stage the work is at, the promised handover date and which payments are due. If something worries you, such as water in the pit, send a photo and a question from the same screen and our office answers you there.

  • One bar for the whole job, so you see how far along it is
  • The next stage and the date we promised
  • Payments tied to progress, shown as paid or due
HLAYour project

Hello, Anita

Example order · Sample villa, Visakhapatnam Now: Rails, cylinder and power pack Promised handover: 15 Dec
  1. Survey and measuring2 Nov
  2. Design and drawings9 Nov
  3. Pit and foundation18 Nov
  4. Shaft and scaffold27 Nov
  5. Rails, cylinder and power pack3 of 5 steps
4 of 7 stages done
Payments

Advance with orderPaid

On delivery to siteDue

On handoverDue

Ask a question or send a photo

Water in the pit, what now?

Our site team has seen your photo and will call you.

Your project: where it is, what comes next, and what is due

Example screens with made-up details, to show how it works.

The emergency-stop rule

Before the car first moves under power, we test the emergency stop and a second person confirms it. The lift stays still until then.

When things change

A project is a conversation.

Homes keep changing while they are built. Tiles and flooring raise the finished floor level, finishes get swapped, and someone always has a better idea once the work starts. That is normal, and we plan for it.

Changes to what was agreed are written down and confirmed with you before we go ahead, so nobody is surprised later. When something is holding the work up, we say what it is and what it needs, whoever's side it is on.

  • Changes in writingAgreed with you before the work goes ahead.
  • Clear responsibilitiesWhat we do and what the builder, electrician or interior team does, set out early.
  • Fix first, then inspect againIf a point fails, we correct it and inspect that point again before the work moves on.
Handover

The day you take the keys.

At handover we walk you through the lift, show you how to use it and demonstrate what to do in an emergency. You receive your keys, including the rescue key, and your documents, and your maintenance arrangements begin.

After that, we are a phone call away.

Next

Ready to shape your lift?

Tell us about your building. We will visit, measure and give you a written plan.

This page describes our general approach. The scope, programme and responsibilities for your project are set out in your quote, drawings and written agreement.